Basic Info
Model NO. | 15ton 6000kva |
Transport Package | Nude, Wooden Cases |
Specification | As per drawing |
Trademark | Ville Industry |
Origin | China |
HS Code | 851300020 |
Production Capacity | 30units Per Year |
Product Description
1. Main technical parameters
SN | Description | Unit | Data |
1 | Rated capacity | T | 15t |
2 | Steel tapping | T | 15-20t |
3 | Diameter of shell | mm | Φ3700 |
4 | Electrode pitch circle diameter | mm | Φ950 |
5 | Electrode diameter | mm | Φ350 (RP) |
6 | Electrode travel stroke | mm | 2600 |
7 | Electrode lifting speed(up/down) | m/min | 6/4 |
8 | Electrode traveling mechanism | | Motor, VVVF |
9 | Max. steel tapping angle (forward) | degree | 42° |
10 | Max. slag tapping angle (backward) | degree | 12° |
11 | Max. roof swivel angle | degree | 60° |
12 | Roof lifting stroke | mm | 400 |
13 | Transformer capacity with water/oil cooler | MVA | 6 |
14 | Transformer primary voltage | kV | 20 |
15 | Transformer secondary voltage | V | 260 - 139 |
16 | Transformer tap changer | | 5 steps, off-load |
17 | Transformer secondary current | A | 13,324 |
18 | Electrode lifting mode | | Hydraulic |
19 | Cooling water circulating flow | T/h | 150 |
2. Scope of Supply
SN | Item | Qty | Remark |
1 | Furnace body | 1 set | |
2 | Tilting mechanism | 1 set | |
3 | Water-cooled roof | 1 set | |
4 | Roof lifting & swivel mechanism | 1 set | |
5 | Conductive arms | 1 set | |
6 | Electrode lifting mechanism | 1 set | |
7 | Cooling water distributor | 1 set | |
8 | Hydraulic power pack | 1 set | Proportional valve and pump make: Parker |
9 | Short net | 1 set | |
10 | L.V. Control system | 1 set | |
11 | PLC control system & HMI | 1 set | Siemens S7-300 |
12 | 6MVA Furnace transformer with water/oil cooler | 1 set | |
13 | Compressed air device | 1 set | |
14 | 10kV H.V. switchboard | 1 set | |
Supplied by the Buyer:1) Installation and installation material, furnace refractory lining, hydraulic medium, lubrication medium and cleaning medium, graphite electrodes;2) Civil works and design (Seller provides furnace foundation drawings and civil work requirements), embedded furnace foundation parts;3) Water supply and gas supply main inlet are laid to Seller's equipment connection point, H.V. incoming line is connected to seller's H.V. switchboard and Transformer terminals, L.V. supply lines are connect to Seller's L.V. power distribution panel.3. Delivery: 4 month after date receiving down payment.WorkshopSales team: